 Performance >> Highlights
July 2010
  • Total 13,592.65 MU has been generated from Indira Sagar Power Station till end of month July' 2010 since inception.
  • The Omkareshwar Power Station generated 80.86 MU against the target of 50.00 MU for the month of July 2010.
  • Topographical Survey of RTPP has been completed.
  • The drilling of bore holes is under progress for Geo-Technical investigation. The samples for lab tests have been collected and deposited with MANIT, Bhopal. Test report is awaited.
  • The scheme of power evacuation is obtained from Madhya Pradesh Power Transmission Co. Ltd., which has been forwarded to NTPC.
  • The action is in progress for obtaining NOC from AAI for RTPP, as per laid down procedures of AAI.
June 2010
  • Indira Sagar Power Station generated 74.62 MU against the target of 61.00 MU during Month of June 2010.
  • Omkareshwar Power Station generated 41.18 MU during the month of June 2010.
May 2010
  • This month ISPS has generated 96.30 MU against the target of 72 MU.
  • Omkareshwar Power Station generated 49.38 MU against the target of 36.00 MU during the month of May 2010.
  • RTPS - Global Tender for the work of availing Consultancy Services for CDM Benefits has been floated on 11-05-2010
April 2010
  • Indira Sagar Power Station generated 159.12 MU against the target of 72.00 MU during Month of April 2010.
  • Omkareshwar Power Station generated 75.57 MU against the target of 35.00 MU during the month of April 2010.
  • The work of preparation of DPR of Reva Thermal Power Station is being carried out by NTPC Ltd.
  • RITES Ltd is being carrying the Consultancy Services for Preparation of Pre Feasibility Report and Detailed Project Report for Coal Transportation & Railway Sidings of Reva Thermal Power Project.
  • Central Water Commission (CWC) has submitted the preliminary report on Hydrological studies
March 2010
  • During the financial year 2009-10, 2118.33 Million units of power generated from Indira Sagar Power Station.
  • The Omkareshwar Power Station generated 952.89 MU against the target of 934.00 MU for the Financial Year 2009-10.
February 2010
  • Indira Sagar Power Station generated 181.86 MU against the target of 150.00 MU during Month of February 2010.
  • Omkareshwar Power Station generated 80.72 MU during the month of Feruary.
  • Work of Social Impact Analysis (SIA) Studies and Base Line Survey of Reva Thermal Power Station has been awarded to Indore School of Social Works on 02-03-2010.
  • The Consultancy Services for Preparation of Pre Feasibility Report and Detailed Project Report for Coal Transportation & Railway Sidings of Reva Thermal Power Project has been awarded.
January 2010
  • Total 12,748.95 MU has been generated from Indira Sagar Power Station till end of year 2009 since inception.
  • The Omkareshwar Power Station generated 132.06 MU against the target of 94.00 MU for the month of January 2010.
  • Central Water Commission has been approached for carrying the Hydrological & Water withdrawal studies for Reva Thermal Power Station Project (RTPP).
  • NHDC has placed order to IIT Roorkee for Site Specific Seismic Studies of the RTPP. The studies are underway.
  • Bids are under evaluation to award the work of Topographical Survey of RTPP Site.
  • Retendering has been done for carrying out Social Impact Assessment and Base line Survey of the Project.